Servelec Controls delivers control & safety system for Sellafield
02 April, 2019
category: Latest News
A vital new Silo Maintenance Facility (SMF) at Sellafield has been officially declared ‘ready for action’. And with the new Nuclear Facility ready to tackle legacy wastes, Servelec Controls is pleased to share the details of its part in the award winning project.
Working on behalf of the SMF Delivery Team (SMFDT) comprised of Cavendish Nuclear and Balfour Beatty JV, Servelec Controls designed, manufactured, tested and delivered the complete control and safety system for the SMF.
The impressive new facility, which has been eight years in the making, will allow Sellafield to empty waste from its legacy Silos, a major priority for the nuclear fuel reprocessing and nuclear decommissioning site.
Servelec Controls’ part in the project took three years to complete and included the detailed design, manufacture and testing of the systems, ultimately delivering over 40 control panel cubicles across nine subsystems. To read more about Servelec Controls’ solution, visit the website.